Closing urban waste deposits in Jud. Alba - Abrud Lot 1-7, Blaj, Cimpeni, Cugir, Ocna Mures 18.11.2014 - 18.11.2015 .[...] Completed   Inside Romania
1996 - 1999 Road infrastructure + suprastructure excepting the asphalt
New bridge 1 piece at Trei Poduri km 373 + 570
Rehabilitation of 10 existing bridges
[...]
Completed   Inside Romania
Dam and HPP Bradisor Anul PIF / Year of commissioning 1981 Dam and HPP Brădişor
The turning into account of the Bradisor storage lake potentiality represents the last stage of the hydroelectric development of the Lotru river.
The works are located on quartz-gneiss. Under the dam, on the right slope and i[...]
Completed   Inside Romania
Design and execution for two transfer stations in Alba County and purchase equipment related to the project Integrated Waste in Alba 2014-2016 Transfer station Blaj - capacity 15,000 tons / year
Ramps download 2 pcs (transfer station with direct download and compaction furniture - press-containers)
Building transfer station S = 6.536 sqm - administrative building - eurocontainer, unloadin[...]
Completed   Inside Romania
Design and execution Highway Sebes-Turda - lot 4 km 53+700-km 64+500 14.09.2014 - 15 mai 2015 Execution technological road 10.8 km, 721,862 sq topsoil stripping, land stabilization foundation, excavation excavations 1,485,005 cubic meters of excavation including stabilization Fillers hydraulic binder 1,129,896 cubic meters, paving the ground [...] Completed   Inside Romania

Semnificatia simbolurilor:
On-going On-going   Completed Completed   Inside Romania Inside Romania   Outside Romania Outside Romania